Parramatta Square

Delivering a 12-week plant room construction program in 9 weeks

The Challenge

Budget constraints, an accelerated program to maintain, and the roof plantroom had limited access, making it “nearly impossible” to install mechanical services conventionally.

The Solution

To meet the program dates, we designed and manufactured over 2,400m of pipework offsite. We installed 85 water-cooled packaged units in modules offsite with pipework, ductwork, and acoustic treatment to enable early commissioning. Multi-system pump/heat exchanger skids were designed and built offsite to allow installation before the roof steel structure was erected.

The Result

HVAC duct and pipe work install, a modular FCU ready to commission, fans and multi-system pump/heat exchanger skids, plus preassembled AHUs directly craned into position.

“Working with PFS significantly reduced our crane time and onsite installation and allowed the 12-week plant room construction to be built in 9 weeks, in a safe manner.”