Budget constraints, an accelerated program to maintain, and the roof plantroom had limited access, making it “nearly impossible” to install mechanical services conventionally.
Parramatta Square
Delivering a 12-week plant room construction program in 9 weeks

The Challenge
The Solution
To meet the program dates, we designed and manufactured over 2,400m of pipework offsite. We installed 85 water-cooled packaged units in modules offsite with pipework, ductwork, and acoustic treatment to enable early commissioning. Multi-system pump/heat exchanger skids were designed and built offsite to allow installation before the roof steel structure was erected.
The Result
HVAC duct and pipe work install, a modular FCU ready to commission, fans and multi-system pump/heat exchanger skids, plus preassembled AHUs directly craned into position.
“Working with PFS significantly reduced our crane time and onsite installation and allowed the 12-week plant room construction to be built in 9 weeks, in a safe manner.”