An aggressive program schedule meant a different approach was required that included constant collaboration with the mechanical and structural engineers and concrete form work contractors.
26MW 3 Storey Data Centre Mechanical Pipework
Innovative framed chilled water pipe modules integrated into the formwork

The Challenge
The Solution
We designed the ‘cast-in’ frame solution to be installed into the wet concrete whilst the form work was underway. This meant that the other trades could commence work immediately and simultaneously on all 3 floors following the stripping of the formwork.
The Result
“Prefab Solutions have been working with our company since establishment on numerous projects. They always meet all requirements of the scope and have delivered all projects on time and budget. Their efforts in engineering, drafting and modelling is superior to all.”